The other copies of the preliminary plat shall be given to such public officials, agencies or utility companies as may be concerned with any phase of improvement in the subdivision. Said certificate or approval shall include a statement that the approval is valid for a period of two years unless extended by the Plan Commission.
Article V Improvements and Requirements
SECTION 28-21 REQUIREMENTS FOR APPROVAL OF FINAL PLAT – No final plat of any subdivision shall be approved unless:
- A certificate of the Board of Public Works and Safety has been filed with the Commission that the improvements listed hereinafter have been installed prior to such approval, and proper record drawings of such installations are filed with the City Engineer, or
-
A certificate of the Board of Public Works and Safety has been filed with the
Commission that a complete set of plans and specifications for the improvements
listed hereinafter has been filed with the Board of Public Works and Safety and that
such plans and specifications are in accordance with the applicable policies and
standards of the Article and a bond to insure the installation of the improvements
as shown by said plans and specifications filed with the Board of Public Works and
Safety for the subdivision has been filed which shall:
- Run to the City of Muncie, Indiana, and
- Be in an amount determined by the Board of Public Works and Safety, subject to the approval of the Commission, to be sufficient to complete the improvements and installations in compliance with this Ordinance, and
- Be with surety satisfactory to the Board of Public Works and Safety, subject to approval of the Commission, and
- Specify the time for the completion of said improvements such time not to exceed two years.
Where the subdivision is located beyond the corporate limits, the Board of County Commissioners of Delaware County would exercise the same authority as the Board of Public Works and Safety.