TABLE N1102.4.1.1 (R402.4.1.1)—continued
AIR BARRIER AND INSULATION INSTALLATIONa
COMPONENT AIR BARRIER CRITERIA INSULATION INSTALLATION CRITERIA
Recessed lighting Recessed light fixtures installed in the building thermal envelope shall be air sealed in accordance with Section N1102.4.5. Recessed light fixtures installed in the building thermal envelope shall be airtight and IC rated, and shall be buried or surrounded with insulation.
Plumbing, wiring or other obstructions All holes created by wiring, plumbing or other obstructions in the air barrier assembly shall be air sealed. Insulation shall be installed to fill the available space and surround wiring, plumbing, or other obstructions, unless the required R-value can be met by installing insulation and air barrier systems completely to the exterior side of the obstructions.
Shower/tub on exterior wall The air barrier installed at exterior walls adjacent to showers and tubs shall separate the wall from the shower or tub. Exterior walls adjacent to showers and tubs shall be insulated.
Electrical/phone box on exterior walls The air barrier shall be installed behind electrical and communication boxes. Alternatively, air-sealed boxes shall be installed.
HVAC register boots HVAC supply and return register boots that penetrate building thermal envelope shall be sealed to the subfloor, wall covering or ceiling penetrated by the boot.
Concealed sprinklers Where required to be sealed, concealed fire sprinklers shall only be sealed in a manner that is recommended by the manufacturer. Caulking or other adhesive sealants shall not be used to fill voids between fire sprinkler cover plates and walls or ceilings.

For SI: 1 inch = 25.4 mm.

a. Inspection of log walls shall be in accordance with the provisions of ICC 400.

b. Air barrier and insulation full enclosure is not required in unconditioned/ventilated attic spaces and at rim joists.