work to be installed within the right-of-way. The County will be responsible only for the review and approval of the utility’s proposal with respect to the locations of the utility facilities to be installed and the manner of installation as related to the County Standards and Specifications. Approval of the permit does not relieve the utility of responsibility for the design. The County does not alter current regulations or authority for installing utilities nor for determining financial responsibility for replacing or adjusting utilities.

5-14-6. Permit Fee.

A permit shall be required for work in the roadway and/or right of way. The following schedule shall be established for all permits:

Type Work to be done Description of Work Amount of Permit Fee Additional costs
Residential Driveway/Mailbox installation $50.00 NONE
Commercial Driveway/Mailbox installation $200.00 Any outside engineering costs required shall be billed to the applicant
Right of Way/Roadway Construction work in the right of way or roadway including road or lane closures and road cuts $100.00 Any outside engineering costs required shall be billed to the applicant
Additional Daily Inspection fee $50 per day for each day of work until completion Any outside engineering costs required shall be billed to the applicant
Drainage Any drainage related activities including culverts, drainage pipes or other work that may affect surface or subsurface water Cost of the permit fee as per Delaware County Storm Water ordinance Any outside engineering costs required shall be billed to the applicant
Overweight and Oversize of vehicles and/or equipment Use of county roads $100.00 Any outside engineering costs required shall be billed to the applicant

Any violation of the terms of this ordinance or the specifications adopted by the County Engineer and/or County Highway Department shall be assumed to require additional inspection and one additional daily permit fee will be assessed for each such infraction.
The requirements for daily permit fees shall end on the day a final inspection by the Engineer verifies that all requirements of this ordinance have been met and, if appropriate, a two-year maintenance bond is in place.

A permit to install facilities in the right-of-way is deemed also a permit to operate and maintain the facilities.

In the event that any action is required to address any maintenance issues during the maintenance period, the contractor shall be responsible for any additional work necessary to maintain the work. If a contractor is required to perform maintenance work, then the contractor shall also be required to secure a daily inspection permit and pay the fee for the time period required to perform the maintenance.

5-14-7. Specifications and Procedure Instructions.

Specifications and Procedural Instructions shall be kept on file in the office of the County Engineer and/or County Highway Department and may be amended from time to time.