locations of the utility facilities to be installed and the manner of installation as related to the County Standards and Specifications. Approval of the permit does not relieve the utility of responsibility for the design. The County does not alter current regulations or authority for installing utilities nor for determining financial responsibility for replacing or adjusting utilities.
5-14-6. Permit Fee. A permit shall be required for work in the roadway. The following schedule shall be established for all permits:
| Type Work to be done | Description of Work | Amount of Permit Fee | Additional costs |
|---|---|---|---|
| Residential | Driveway/Mailbox installation | $50.00 | NONE |
| Commercial | Driveway/Mailbox installation | $200.00 | Any outside engineering costs required shall be billed to the applicant |
| Roadway | Construction work in the roadway including road or lane closures and road cuts | $100.00 | Any outside engineering costs required shall be billed to the applicant |
| Additional Daily Inspection fee | $50 per day for each day of work until completion | Any outside engineering costs required shall be billed to the applicant | |
| Drainage | Any drainage related activities including culverts, drainage pipes or other work that may affect surface or subsurface water | Cost of the permit fee as per Delaware County Storm Water ordinance | Any outside engineering costs required shall be billed to the applicant |
| Overweight and Oversize of vehicles and/or equipment | Use of county roads | $100.00 | Any outside engineering costs required shall be billed to the applicant |
Any violation of the terms of this ordinance or the specifications adopted by the County Engineer and/or County
Highway Department shall be assumed to require additional inspection, and one additional daily permit fee will be assessed for each such infraction.
The requirements for daily permit fees shall end on the day a final inspection by the Engineer verifies that