Exhibit A

Resolution 26-29 & 26-30

*All estimates are rounded to the nearest 1,000

Original Listing

Des# Contract # Sponsor Description, Work Type, & Performance Measure Year Phase Funding Amount Funded by Funding Program/ Category Est. Total Cost Complete by Phase and Year Est. Project Total
2300871 45154 INDOT NB Bridge over abandoned RR, 03.16 mi (I-69) (Bridge Replacement) (AQC exempt: 06/20/25) 2026 PE $350,753 Federal STBG $389,725 $65,579,025
2026 PE $38,973 State State

Proposed Listing

Des# Contract # Sponsor Description, Work Type, & Performance Measure Year Phase Funding Amount Funded by Funding Program/ Category Est. Total Cost Complete by Phase and Year Est. Project Total Resolution
2300871 R-45154 INDOT I-69 NB Bridge over abandoned RR, 03.16 mi (I-69) (Bridge Replacement) (AQC exempt: 06/20/25)
Note: Move PE of $389,725 from FY26 to FY27 and update the funding category to NHS; Add new phase of CN of
2027 PE $350,753 Federal NHS $389,725 $5,051,000 Res 26-29
2027 PE $38,973 State State
2028 CN $3,515,000 Federal NHS $3,906,000 Res 26-30
2028 CN $391,000 State State