Resolution 26-18
Exhibit A
*All estimates are rounded to the nearest 1,000
Des# Contract # Sponsor Description, Work Type, & Performance Measure Year Phase Funding Amount Funded by Funding Program/ Category Est. Total Cost Complete by Phase and Year Est. Project Total
2200791 B-44566 INDOT I-69 NB Bridge over N&S RR (CR 251) 0.66 mi N of SR332 (Bridge Deck Replacement)(Bridge Condition) (AQC exempt 03/27/25, 2/11/26) 2027 CN $1,615,000 Federal NHS $1,795,000 $8,122,000
2200791 B-44566 INDOT I-69 NB Bridge over N&S RR (CR 251) 0.66 mi N of SR332 (Bridge Deck Replacement)(Bridge Condition) (AQC exempt 03/27/25, 2/11/26) 2027 CN $180,000 State State $1,795,000 $8,122,000
Proposed Listing
Des# Contract # Sponsor Description, Work Type, & Performance Measure Year Phase Funding Amount Funded by Funding Program/ Category Est. Total Cost Complete by Phase and Year Est. Project Total
2200791 B-44566 INDOT I-69 NB Bridge over N&S RR (CR 251) 0.66 mi N of SR332 (Bridge Deck Replacement)(Bridge Condition) (AQC exempt 03/27/25, 2/11/26) 2027 CN $1,852,000 Federal NHS $2,058,000 $9,936,000
2200791 B-44566 INDOT I-69 NB Bridge over N&S RR (CR 251) 0.66 mi N of SR332 (Bridge Deck Replacement)(Bridge Condition) (AQC exempt 03/27/25, 2/11/26)
Increased FY27 CN by $263,000 (increased federal by $237,000 and state by $26,000)
2027 CN $206,000 State State $2,058,000 $9,936,000