Fiber optic installation work is being done on the north side of town along W. Schantz Avenue. This is part of the fiber optic network project managed by Miami Valley Cable Council (MVCC).
Mayor Duncan asked when East Drive will be resurfaced.
Mr. Klopsch shared that work on East Drive started today and the milling will be done tomorrow. The street will be renewed with asphalt. The City reached an agreement with Vectren to pay for this work due to the extensive pavement damage resulting from gas line work they completed last fall. Vectren will pay $38,592 directly to the contractor.
COUNCIL COMMENTS – NONE
The public meeting concluded at 8:40 p.m.