Exclusions:

  • Construction labor and materials
  • Permit and agency fees
  • Specialty testing unless specifically authorized
  • Environmental or hazardous materials assessments

These services can be added by amendment if required.

Schedule

Upon authorization to proceed, BW Construction anticipates:

  • Initial plan and site review: 2–3 weeks
  • Development of compliant revisions: 6-8 weeks for initial
  • Subsequent Drawing Revisions 2-4 Weeks
  • Permit support and AHJ coordination: As required by review timelines

A detailed schedule can be provided upon notice to proceed.

Fee Proposal

Fees for the services outlined herein will be provided as a not-to-exceed amount of $47,500.00. Any additional services will be addressed through written authorization.

  • Architectural, Structural, & MEPF Services (DCCM) NTE $35,000.00
  • DCCM Code Compliance Services (DCCM Consultant) NTE $5,000.00
  • BW Consulting Services NTE $7,500.00

Hourly Rate Sheets will be provided prior to execution of Contract for Services to be billed.

Acceptance

BW Construction appreciates the opportunity to submit this proposal and looks forward to assisting Delaware County in bringing the Justice Center into full compliance while maximizing functional use of its facilities.