Current Listing
| Des# | Contract # | Sponsor | Description, Work Type, & Performance Measure | Year | Phase | Funding Amount | Funded by | Funding Program/ Category | Est. Total Cost Complete by Phase and Year | Est. Project Total |
|---|---|---|---|---|---|---|---|---|---|---|
| 2301137 | R-45154 | INDOT | From 0.08 mi S of US 35/SR 28 to 0.41 mi S of SR 26 inc bridges over NB/SB Abandoned RR, NB over Pipe Creek, over US 35/SR 28 and SR 28 over US35/SR 28 (HMA Overlay Minor Structural) (Roadway) (AQC exempt: 06/20/25) | 2026 | PE | $5,055,000 | Federal | NHS | $5,617,000 | $68,620,723 |
| $562,000 | State | State | ||||||||
| 2027 | PE | $2,397,000 | Federal | NHS | $2,633,000 | |||||
| $266,000 | State | State | ||||||||
| 2028 | CN | $41,459,082 | Federal | NHPP | $46,066,000 | |||||
| $4,606,565 | State | State | ||||||||
| From 0.08 mi S of US 35/SR 28 to 0.41 mi S of SR 26 inc bridges over NB/SB Abandoned RR, NB over Pipe Creek, over US 35/SR 28 and SR 28 over US35/SR 28 (HMA Overlay, Structural) (Bridge) (AQC exempt: 06/20/25) | 2028 | CN | $8,921,590 | Federal | NHPP | $9,913,000 | ||||
| $991,288 | State | State |
Est. Project Total: $68,620,723
Description: From 0.08 mi S of US 35/SR 28 to 0.41 mi S of SR 26 inc bridges over NB/SB Abandoned RR, NB over Pipe Creek, over US 35/SR 28 and SR 28 over US35/SR 28 (HMA Overlay Minor Structural) (Roadway) (AQC exempt: 06/20/25)
2026 - PE
Est. Phase Total: $5,617,000
| Funded by | Program | Amount |
|---|---|---|
| Federal | NHS | $5,055,000 |
| State | State | $562,000 |
2027 - PE
Est. Phase Total: $2,633,000
| Funded by | Program | Amount |
|---|---|---|
| Federal | NHS | $2,397,000 |
| State | State | $266,000 |
2028 - CN
Est. Phase Total: $46,066,000
| Funded by | Program | Amount |
|---|---|---|
| Federal | NHPP | $41,459,082 |
| State | State | $4,606,565 |
Description: From 0.08 mi S of US 35/SR 28 to 0.41 mi S of SR 26 inc bridges over NB/SB Abandoned RR, NB over Pipe Creek, over US 35/SR 28 and SR 28 over US35/SR 28 (HMA Overlay, Structural) (Bridge) (AQC exempt: 06/20/25)
2028 - CN
Est. Phase Total: $9,913,000
| Funded by | Program | Amount |
|---|---|---|
| Federal | NHPP | $8,921,590 |
| State | State | $991,288 |
Proposed Listing
| Des# | Contract # | Sponsor | Description, Work Type, & Performance Measure | Year | Phase | Funding Amount | Funded by | Funding Program/ Category | Est. Total Cost Complete by Phase and Year | Est. Project Total |
|---|---|---|---|---|---|---|---|---|---|---|
| 2301137 | R-45154 | INDOT | From 0.08 mi S of US 35/SR 28 to 0.41 mi S of SR 26 (HMA Overlay, Structural) (Roadway) (AQC exempt: 06/20/25) | 2026 | PE | $5,055,000 | Federal | NHS | $5,617,000 | $68,620,723 |
| $562,000 | State | State | ||||||||
| 2027 | PE | $2,397,000 | Federal | NHS | $2,633,000 | |||||
| $266,000 | State | State | ||||||||
| 2028 | CN | $58,927,000 | Federal | NHS | $65,475,000 | |||||
| $6,547,565 | State | State |
Est. Project Total: $68,620,723
Description: From 0.08 mi S of US 35/SR 28 to 0.41 mi S of SR 26 (HMA Overlay, Structural) (Roadway) (AQC exempt: 06/20/25)
2026 - PE
Est. Phase Total: $5,617,000
| Funded by | Program | Amount |
|---|---|---|
| Federal | NHS | $5,055,000 |
| State | State | $562,000 |
2027 - PE
Est. Phase Total: $2,633,000
| Funded by | Program | Amount |
|---|---|---|
| Federal | NHS | $2,397,000 |
| State | State | $266,000 |
2028 - CN
Est. Phase Total: $65,475,000
| Funded by | Program | Amount |
|---|---|---|
| Federal | NHS | $58,927,000 |
| State | State | $6,547,565 |
Note / Explanation
Increase FY28 Roadway CN in the amount of $19,409,000; Remove FY28 Bridge CN and distribute it through out secondary des numbers within the contract (The new secondary des numbers under this contract do not all align with those eligible for group modifications, so they have been separated in the DMTIP)