Detention Pond/Basin: Temporarily stores stormwater runoff and releases it at a controlled rate; requires alternative standards.

Flood Zone: A geographical area with a specific flood risk, categorized by the likelihood and impact of flooding.

Injunctive Relief: Court ordered remedy which restricts a party from committing specific actions or requires party to complete specific actions.

Legally Non-Conforming: Legal land use that occurred prior to Ordinance Adoption, revision, or amendment.

Retention Pond/Basin: Permanent body of water designed to collect and store stormwater runoff; requires alternative standards.

Road Right-of-Way: An area where there are rights to pass over or through real property owned by someone else; related to "easement".

Septic Field: Any subsurface wastewater disposal facility used to remove contaminants and impurities from the liquid that emerges after anaerobic digestion in a Septic Tank.

Severability: A contractual or statutory provision that allows for invalidation of one or more parts of an agreement or law without affecting validity of remaining document.

Spillway: structure designed to safely release excess water from water impoundment.

Stop Work Order: Formal directive issued by authorized authority, requiring contractor to immediately halt all or part of project.

Wetlands: An area saturated by surface or ground water sufficient to support vegetation adapted for life in saturated soil conditions.

Article 2. Pond Development Protocol
Section 1. Pond Requirements and Site Design.
  1. A Pond Compliance permit shall be required for the construction or enlargement of all private residential or farm ponds. The property owner shall submit a permit application to the Delaware County Building Commissioners' Office. The application shall be accompanied by a site plan that demonstrates compliance with subsections 2 through 19.
  2. Site plan must include all measurements involved with the job. Plans must indicate:
    1. North with arrow
    2. Buildings
    3. Wells, Septic field, utility structures will require professional locating services
    4. Road right of way
    5. Drainage
    6. Utility easements
    7. Flood zones and wetlands; if indicated, further documentation will be required.
    8. Size and depth of pond
    9. Shore contours
  3. Ponds shall be setback a minimum of 75 feet from any public roadway as measured from the proposed or actual right-of-way, whichever is greater, to the top of the bank of the pond, unless otherwise approved.
  4. If approved, any pond constructed within the setback must be protected by a highway barrier guard rail that meets INDOT specifications. Guardrail must be maintained by property owner.