| Des# | Contract# | Sponsor | Description, Work Type, & Performance Measure |
Year | Phase | Funding Amount |
Funded by | Funding Program/ Category |
Est. Total Cost Complete by Phase and Year |
Est. Project Total |
|---|---|---|---|---|---|---|---|---|---|---|
| 2300290 | INDOT | Tunnels throughout the state (Bridge Inspections) (Bridge Condition) (AQC exempt 03/27/25) |
2027 | PE | $310,400 | Federal | STBG | $388,000 | $1,388,000 | |
| 2300290 | INDOT | Tunnels throughout the state (Bridge Inspections) (Bridge Condition) (AQC exempt 03/27/25) |
2027 | PE | $77,600 | INDOT | State | $388,000 | $1,388,000 | |
| 2300691 | R-45192 | INDOT | On US 35 from CR 875 W to 520 ft East of CR 875 W (MM 245) (Access Control) (Mobility) (AQC exempt status: 03/27/25, 1/6/26) |
2027 | RW | $18,000 | Federal | NHPP | $20,000 | $204,000 |
| 2300691 | R-45192 | INDOT | On US 35 from CR 875 W to 520 ft East of CR 875 W (MM 245) (Access Control) (Mobility) (AQC exempt status: 03/27/25, 1/6/26) |
2027 | RW | $2,000 | INDOT | State | $20,000 | $204,000 |
| 2300691 | R-45192 | INDOT | On US 35 from CR 875 W to 520 ft East of CR 875 W (MM 245) (Access Control) (Mobility) (AQC exempt status: 03/27/25, 1/6/26) |
2029 | CN | $46,246 | Federal | NHPP | $51,000 | $204,000 |
| 2300691 | R-45192 | INDOT | On US 35 from CR 875 W to 520 ft East of CR 875 W (MM 245) (Access Control) (Mobility) (AQC exempt status: 03/27/25, 1/6/26) |
2029 | CN | $5,138 | INDOT | State | $51,000 | $204,000 |
| 2300704 | 45194 | INDOT | SR 332 at CR 500 W (Intersection Improvement w/ added turn lanes) (Safety) (AQC exempt 03/27/25) |
2030 | CN | $442,046 | Federal | STBG | $553,000 | $553,000 |
| 2300704 | 45194 | INDOT | SR 332 at CR 500 W (Intersection Improvement w/ added turn lanes) (Safety) (AQC exempt 03/27/25) |
2030 | CN | $110,512 | INDOT | State | $553,000 | $553,000 |