| 2300870 | R-45154 | INDOT | I-69 SB Bridge over PIPE CREEK, 03.95 mi N SR 28 (Bridge Deck Overlay) (Bridge) |
2028 | CN | $211,000 | Federal | NHS | $235,000 | $235,000 |
| 2300870 | R-45154 | INDOT | I-69 SB Bridge over PIPE CREEK, 03.95 mi N SR 28 (Bridge Deck Overlay) (Bridge) |
2028 | CN | $24,000 | INDOT | State | $235,000 | $235,000 |
| 2300871 | 45154 | INDOT | NB Bridge over abandoned RR, 03.16 mi (I-69) (Bridge Replacement) (AQC exempt: 06/20/25) |
2027 | PE | $350,753 | Federal | NHS | $389,725 | $5,051,000 |
| 2300871 | 45154 | INDOT | NB Bridge over abandoned RR, 03.16 mi (I-69) (Bridge Replacement) (AQC exempt: 06/20/25) |
2027 | PE | $38,973 | INDOT | State | $389,725 | $5,051,000 |
| 2300871 | 45154 | INDOT | NB Bridge over abandoned RR, 03.16 mi (I-69) (Bridge Replacement) (AQC exempt: 06/20/25) |
2028 | CN | $3,515,000 | Federal | NHS | $3,906,000 | $5,051,000 |
| 2300871 | 45154 | INDOT | NB Bridge over abandoned RR, 03.16 mi (I-69) (Bridge Replacement) (AQC exempt: 06/20/25) |
2028 | CN | $391,000 | INDOT | State | $3,906,000 | $5,051,000 |
| 2300872 | R-45154 | INDOT | I-69 SB Bridge over Abandoned RR, 03.16 mi S SR 26 (Bridge Replacement, Other Construction) (Bridge) |
2028 | CN | $3,515,000 | Federal | NHS | $3,906,000 | $3,906,000 |
| 2300872 | R-45154 | INDOT | I-69 SB Bridge over Abandoned RR, 03.16 mi S SR 26 (Bridge Replacement, Other Construction) (Bridge) |
2028 | CN | $391,000 | INDOT | State | $3,906,000 | $3,906,000 |
| 2301079 | R-45195 | INDOT | US 35 at CR 300 S (0.26 miles) (Intersection Improvement, Roundabout) (Safety) (AQC exempt 02/07/24, 2/11/26) |
2026 | PE | $257,000 | Federal | HSIP | $285,000 | $2,968,000 |
| 2301079 | R-45195 | INDOT | US 35 at CR 300 S (0.26 miles) (Intersection Improvement, Roundabout) (Safety) (AQC exempt 02/07/24, 2/11/26) |
2026 | PE | $28,000 | INDOT | State | $285,000 | $2,968,000 |