*Fiscal Year 30 is illustrative.
Scroll horizontally to view the full table
| Des# | Contract# | Sponsor | Description, Work Type, & Performance Measure |
Year | Phase | Funding Amount |
Funded by | Funding Program/ Category |
Est. Total Cost Complete by Phase and Year |
Est. Project Total |
|---|---|---|---|---|---|---|---|---|---|---|
| 2200995 | 44608 | INDOT |
District Wide Pedestrian Crossings
(Bike & Pedestrian Facilities) (Safety) (AQC exempt: 3/27/25, 2/11/26) |
2027 | CN | $245,907 | INDOT | State | $1,494,000 | $1,977,000 |
| 2201151 | 43945 | INDOT |
From I-69 to 3.76 mile W of SR 3
(CR 400 S) MMCOG, IMPO, DMMPC, No Rural (Traffic Signals Modernization) (Safety Construction) (AQC exempt 03/27/25, 2/11/26) |
2026 | PE | $31,000 | Federal | HSIP | $34,000 | $1,399,000 |
| 2201151 | 43945 | INDOT |
From I-69 to 3.76 mile W of SR 3
(CR 400 S) MMCOG, IMPO, DMMPC, No Rural (Traffic Signals Modernization) (Safety Construction) (AQC exempt 03/27/25, 2/11/26) |
2026 | PE | $3,000 | INDOT | State | $34,000 | $1,399,000 |
| 2201151 | 43945 | INDOT |
From I-69 to 3.76 mile W of SR 3
(CR 400 S) MMCOG, IMPO, DMMPC, No Rural (Traffic Signals Modernization) (Safety Construction) (AQC exempt 03/27/25, 2/11/26) |
2026 | CN | $987,276 | Federal | STBG | $1,234,000 | $1,399,000 |
| 2201151 | 43945 | INDOT |
From I-69 to 3.76 mile W of SR 3
(CR 400 S) MMCOG, IMPO, DMMPC, No Rural (Traffic Signals Modernization) (Safety Construction) (AQC exempt 03/27/25, 2/11/26) |
2026 | CN | $246,819 | INDOT | State | $1,234,000 | $1,399,000 |
| 2201179 | INDOT |
Statewide Cell Service for
Communications for Signals and ITS Devices for FY 26 (ITS Operations & Maintenance Contracts) (CMAQ) (AQC exempt status 3/27/25) |
2026 | PE | $1,000,000 | Federal | STBG | $1,250,000 | $1,250,000 | |
| 2201179 | INDOT |
Statewide Cell Service for
Communications for Signals and ITS Devices for FY 26 (ITS Operations & Maintenance Contracts) (CMAQ) (AQC exempt status 3/27/25) |
2026 | PE | $250,000 | INDOT | State | $1,250,000 | $1,250,000 |