1
PROJECT TITLE
2
PROJECT
NUMBER
3
ESTIMATED
TOTAL
COST
4
AMOUNTS
RESERVED
IN PRIOR
YEARS
PLANNED FUNDING SERVICES FOR CURRENT YEAR - 2025
6
TO BE
FUNDED IN
FUTURE
YEARS
5a
2025 Budget
Appropriations
5b
Capital
Improvement Fund
5c
Capital
Surplus
5d
Grants in Aid and
Other Funds
5e
Debt
Authorized
EQUIPMENT: -
FIRE: -
TURNOUT GEAR - FIRE DEPARTMENT 20,500.00 20,500.00
SCBA MASK FIT TEST MACHINE 11,000.00 11,000.00
APPARTUS EMERGENCY LIGHTS 42,500.00 42,500.00
TURNOUT GEAR - FIRE OFFICIAL 6,100.00 6,100.00
KNOX BOXES 18,500.00 18,500.00
-
POLICE: -
RECORDS SCANNING PROJECT 57,400.00 57,400.00
TASERS 75,000.00 75,000.00
TOUGH BOOKS ( COMPUTERS FOR CARS) 23,000.00 23,000.00
RADAR UNITS 7,800.00 7,800.00
PATROL/ STORM UTILITY VEHICLE 75,000.00 75,000.00
POWER DMS UNIT 7,500.00 7,500.00
-
-
-
TOTAL - THIS PAGE XXXXX 344,300.00 - - 344,300.00 - - - -
Sheet 40b1
C - 3