DESCRIPTION OF MOVING (REF. 5.3.):
- Hoist bell with tractor on existing bell mount using padded nylon straps, set on padded pallet on trailer.
- Cut existing foundation away to remove supporting limestone fingers. Palleted by hand.
- Relocation using padded pallets by truck and trailer.
TIMELINE (REF 6.):
- April 3rd – May 1st
- Depending on weather conditions preparation will begin April 3rd
- New foundation will be set
- Deconstruction will ensue
- Relocation
- Reconstruction and placement
- Fixing existing sites concrete
More detailed timeline per item will be given closer to date.
RELATIVE EXPERIENCE:
Building since 1988. More than a million square feet ground up new commercial construction.
Thousands of yards of concrete work. Using cranes to move a ship, many steel and pre-cast members, and planning mobilization of all construction equipment; Including 200-ton mobile cranes.
INSURANCE:
A job specific policy will be obtained and provided upon acceptance.
QUOTE:
| Item | Price |
|---|---|
| Labor | $7,500.00 |
| Equipment | $5,000.00 |
| Material | $5,500.00 |
| Administrative | $4,000.00 |
| Total | $22,000.00 |