MUNCIE CONSTRUCTION
DESCRIPTION OF MOVING (REF. 5.3.):
  • Hoist bell with tractor on existing bell mount using padded nylon straps, set on padded pallet on trailer.
  • Cut existing foundation away to remove supporting limestone fingers. Palleted by hand.
  • Relocation using padded pallets by truck and trailer.
TIMELINE (REF 6.):
  • April 3rd – May 1st
    1. Depending on weather conditions preparation will begin April 3rd
    2. New foundation will be set
    3. Deconstruction will ensue
    4. Relocation
    5. Reconstruction and placement
    6. Fixing existing sites concrete

More detailed timeline per item will be given closer to date.

RELATIVE EXPERIENCE:

Building since 1988. More than a million square feet ground up new commercial construction.
Thousands of yards of concrete work. Using cranes to move a ship, many steel and pre-cast members, and planning mobilization of all construction equipment; Including 200-ton mobile cranes.

INSURANCE:

A job specific policy will be obtained and provided upon acceptance.

QUOTE:
Item Price
Labor $7,500.00
Equipment $5,000.00
Material $5,500.00
Administrative $4,000.00
Total $22,000.00