owner/operator's sole expense. The inspector will ensure that all drainage infrastructure was installed according to specifications of the drainage plans and according to the requirements in the Stormwater Management Ordinance and Stormwater Quality Management Plan. any additional.
4. Groundwater Monitoring
Prior to construction, the owner/operator shall engage at the owner/operators' expense an independent third party to develop a groundwater monitoring program within the fence line of the solar facility which will include, but not be limited to, the establishment of baseline levels of ground water quality and for monitoring to continue annually for the life of the project, with the final monitoring taking place within six (6) months after the completion of decommissioning. The results of the monitoring program are to be submitted to the DMMPC Executive Director within thirty (30) days of the owner/operator receiving the results from each monitoring every two years or in event of breakage of panels through storms or accidents or at the request of the DMMPC Executive Director. Results shall also be provided to any necessary government agencies as required by law.
5. Construction Requirements
-
a.
During construction, the applicant shall demonstrate and document to the satisfaction of the County, County Highway Superintendent, County Surveyor, Executive Director and any other person(s) designated and authorized by the County Commissioners, that the following requirements are met:
-
b.
All reasonable dust control measures required by the County Commissioners during construction of the solar facility are being followed together with any additional steps or adjustments for dust control which may
from time to timebe required by the County Commissioners. -
c.
Reasonable storm water best management practices as required by the approved Drainage Plan/Agreement.
-
d.
Near a residence or public use noise shall be kept to a minimum from dusk to dawn.
6. Post-Construction Requirement for a solar facility
Post-construction, the applicant shall comply with the following provisions:
-
a.
Road Repairs: Any road damage caused by the transport of any matter or material utilized in any way regarding the solar facility, in the construction of the solar facility, the installation of the same, and/or the removal and decommissioning of the same, shall be repaired to the satisfaction of Delaware County (as per the Road Use and Maintenance Agreement). The County may choose to require either remediation of road(s) upon completion of the solar facility or may, by ordinance, collect fees for oversized load permits.
-
b.
As Built Plan Requirements: Where upon completion of all development, the exact measurements of the location of utilities, structures and components erected during the development are necessary for public record and shall therefore be