Program 300: Short Range Planning & Management Systems
| FY 2026 Funding Summary | Program 300 | |||
|---|---|---|---|
| Funding Source | Budget | Expenditures | Overage |
| PL/FTA | $40,000 | $167,072.12 | $127,072.12 |
| Local | $10,000 | $41,768.03 | $31,768.03 |
| Total | $50,000 | $208,840.15 | $158,840.15 |
*Explanation of overage included on page 18
Objectives
Develop, update, and maintain a fiscally constrained four-year Delaware-Muncie Transportation Improvement Program (DMTIP) for the Metropolitan Planning Area (MPA)
Implement transportation management systems that support data-driven investment decisions, system performance, and public transparency.
Support compliance with federal planning requirements, implementation of the Muncie Intelligent Transportation System (ITS) Architecture, and adherence to the Manual on Uniform Traffic Control Devices (MUTCD).
Accomplishments
- Worked with maps in GIS
- Livestreamed meetings to the County website
- Prepared DMTIP amendments and modifications
- Prepared the Annual List of Obligated Projects (ALOP)
- Maintained and updated zoning and address information
Meetings
-
Project Planning (x1)
-
Bridge Funding Update (x8)
-
Bridge Selection Scoring (x1)
-
Quarterly Project Tracking (x4)
-
Culvert Inventory Discussion (x1)
End Product
Completed Projects (FY26)
- Delaware-Muncie Transportation Improvement Program (DMTIP) – The FY 2026-2030 DMTIP preparation began in FY 2025, and the final document was approved in July 2025.
- Annual List of Obligated Projects (ALOP) – The FY 2025 ALOP preparation began in early September, 2025. The document was completed and submitted to INDOT in late September, 2025.
Upcoming Projects (FY27)
- Delaware-Muncie Transportation Improvement Program (DMTIP) – Ongoing amendments & modifications.
- Annual List of Obligated Projects (ALOP) – The FY 2026 ALOP preparation began in early September, 2026. It was completed in late September, 2026.