Program 600: Other Planning Initiatives
| FY 2026 Funding Summary | Program 600 | |||
|---|---|---|---|
| Program 600 | Budget | Expenditures | Overage |
| PL/FTA | $18,269 | $59,633.35 | $41,364.35 |
| Local | $4,567.25 | $14,908.34 | $10,341.09 |
| Total | $22,836.25 | $74,541.69 | $51,705.44 |
Scroll horizontally to view all funding columns.
*Explanation of overage included on page 18
Objectives
The purpose of this program is to enhance technical capabilities to guide transportation network upgrades for short-and long-range needs. Activities include corridor studies, land use coordination, and ADA transition planning. All studies will follow federal guidelines for purpose and need and streamline NEPA requirements where applicable.
Accomplishments
- Revised Ordinances
- Reviewed RFP proposals
- Wrote an article for MAP
- Reviewed UDO Proposals
- Reviewed ADA compliance
- Conducted site plan reviews
- Prepared the ADA Title VI Plan
- Developed the Ordinance Update
- Managed ADA-related correspondence
- Reviewed Solar Ordinance Amendments
- Delivered a Comprehensive Plan presentation
- Attended City Council for subdivision amendment introduction
- Attended the MAP Annual Report to the Community presentation
Meetings
-
MAP Board (x4)
-
ADA Title VI Public (x1)
-
MAP Executive Board (x2)
-
ADA Working Committee (x1)
End Product
Completed Projects (FY26)
- ADA Transition Plan – Preparation for the ADA Transition Plan began in FY2025. The project was completed in August, 2025.
- ADA Title VI Plan – Updated August 2025.
Upcoming Projects (FY27)
- Ordinance Updates – UDO ordinance update began July 2026 and is estimated to continue through September 2027.