Project and Survey Limits

Delaware County Bridge 5 on CR W 850 N. over Creek. The field survey limits will consist of the following:

  • Project corridor length (E-W) is 500 feet in length (250 feet east and 250 feet west of the existing structure.
  • Project corridor width (N-S) is edge of pavement to edge of pavement
  • The stream corridor (N-S) is 500 feet in length (250 feet north and 250 feet south of the existing structure.
  • The stream corridor width includes from the top of the stream bank to the top of the stream bank and 75 feet wide beyond the top of the bank on both sides of the stream banks.
  • Provide cross section of the stream at 50 feet interval.

Please see Exhibit 1 for topographic survey limits.

D.
Obtain physical data of the existing bridge including opening, elevations and provide sketch of the existing structure opening on both ends.
E.
Obtain Local Testimony of flood HW elevation and year (if the information is available.)
F.
Obtain last deed of record, subdivision plats and section or auditor plats for all properties within the project limits from local and state agencies. The property information shall include parcel number, property owner’s name, mailing address and property location. APEX shall provide a listing of all property information, deeds, plats and maps.
G.
Send out survey notices together with questionnaires (if applicable) to all property owners adjacent to the proposed LCRS’s and TOPO sections within the project area. All survey notices and questionnaires shall be approved by Client prior to distribution.
H.
Establish Primary Horizontal Control within the project limits such that the survey base line(s) can be re-established during construction. The coordinate system will be the Delaware County