Base Bid: Roof Area #6: We propose to provide the New Carlisle Syntec Systems .060 Sure-Seal Adhered EPDM System over new ½ “ Secureshield HD cover board per the provided bidding specifications and scope of work for the sum of:

Dollars ($)

Base Bid to Also Include: Bidders to include an allowance of $10,000.00 for cost of removing abandoned equipment, infill with mew decking, etc. Should these funds not be needed, they will be returned to the building owner or used for other unforeseen items associated with the project. All items are to be approved by building owners’ representative.

Unit Costs Additions (are for reference during construction):

+ Steel Deck replacement as needed (documentation required) $/SF
+ Wood Blocking (material & labor) $/BF
+ Drain Bowl Assembly replacement as needed $/EA
+ Additional Walkway Pads Installed (pad & labor) $/LF
+ Wire brush and painting of rusted decking per 100 sf $/SF
NAME OF BIDDER (Corporate Name)
SIGNATURE (Corporate Office)
DATE SIGNED
12