| Action Item | Responsible Party / Detail | Est. Timeframe |
|---|---|---|
| Insurance & liability | Applicant secures general liability and property insurance naming the county as additional insured prior to any public access | Days 60 – 120 |
| Tax break application | Applicant applies for applicable property tax abatement/historic preservation tax incentives, effective upon completion of Phase 5 | Ongoing through Phase 5 |
This photo reflects the intended gating and signage approach for Phase 1. Exact placement, hardware, and materials will be finalized with the County during permitting and are subject to approval before installation.
PHASE 2 Permanent Gates & Private Financing
GOAL
Replace temporary safety measures with permanent infrastructure, and secure private capital — not county funds — to fund the venue build-out planned in later phases.
Permanent entrance gate and covered gazebo structure envisioned for the bridge approach.
| Action Item | Responsible Party / Detail | Est. Timeframe |
|---|---|---|
| Permanent gate installation | Fabricated steel gates at both bridge entrances, keyed access for staff/emergency services, ADA-compliant pedestrian access for approved events | Months 7 – 9 |