Approval Action for the Project for the purposes of the CEQA pursuant to San Francisco Administrative Code Section 31.04(h). The Commission will rely on the determination of the Planning Department to make its decision on this action. |
| 26-0081 |
5/26/2026 |
JOC-105 |
Approve Modification No. 1 to Job Order Contract No. JOC-105, General Building (B License) Construction, San Francisco, San Mateo, Santa Clara, and Alameda Counties, with Rubecon General Contracting, Inc., to increase the contract not-to-exceed amount by $2,500,000, and increase the contract duration by three years, for a revised not-to-exceed contract amount of $7,500,000 and a total contract duration of five years, to provide additional capacity and time for facility and asset improvements. |
| 26-0082 |
5/26/2026 |
Purchase and Sale Agreement and Easement Deed with Associated Limousine Operators of San Francisco, Inc. |
Approve the terms and conditions and authorize the General Manager and/or City’s Director of Property to execute a Purchase and Sale Agreement and Easement Deed with Associated Limousine Operators of San Francisco, Inc., for the acquisition of an approximately 4,500-square-foot Sewer Tunnel Easement and an approximately 3,400-square-foot Restricted Development Easement on and across property located at 1398 Bryant Street, San Francisco, California, designated as a portion of San Francisco Assessor’s Parcel 3923-002, for $1,454,926, subject to Board of Supervisors and Mayor approval. |
| 26-0083 |
5/26/2026 |
HH-1005 |
Approve an increase of 418 calendar days to the existing duration contingency for Contract No. HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements: Phase 1A, with Sierra Mountain Construction, Inc., for a revised duration limit of 1,506 consecutive calendar days (approximately four years), with no change to the contract amount, to allow additional time for evaluation and coordination associated with the Phase 2 knife gate valves procured under this contract and closeout activities. |
| 26-0084 |
5/26/2026 |
HH-1000R |
Approve an increase of $15,000,000 to the existing cost contingency for Contract No. HH-1000R, Mountain Tunnel Improvements Project, with Mountain Tunnel Constructors, Inc., for a revised cost limit of $165,173,126, to address additional costs resulting from a delayed start and earlier end to Outage No. 5 in 2025-26, delayed initial commissioning of the Flow Control Facility due to design changes to critical electrical equipment, delayed final project commissioning due to additional work required from the descoping of South Fork, and anticipated additional costs to resolve outstanding potential change orders, with no change to the contract duration limit. |