SHROYER ROAD DIET
CITY OF OAKWOOD
Construction Estimate (Worksheet)
Approximate project length = 1.11 miles
DESCRIPTION QTY. UNIT UNIT COST COST NOTES
Sta. 23+50 to Sta. 25+00 - EACH $75 $0 Broad - Wonderly
Sta. 25+00 to Sta. 28+50 3 EACH $75 $225 Wonderly - Orchard
Sta. 28+50 to Sta. 32+00 3 EACH $75 $225 Oarchard - Triangle
Sta. 32+00 to Sta. 35+50 3 EACH $75 $225 Triangle - Peach Orchard
Sta. 35+50 to Sta. 38+50 3 EACH $75 $225 Paeach Orachard - Monteray
Sta. 38+50 to Sta. 41+50 3 EACH $75 $225 Monteray - Hadley
Sta. 41+50 to Sta. 45+00 3 EACH $75 $225 Hadley - Corona
Sta. 45+00 to Sta. 48+50 3 EACH $75 $225 Corona - Wiltshire
Sta. 48+50 to Sta. 51+50 3 EACH $75 $225 Wiltshire -Telford
Sta. 51+50 to Sta. 55+00 3 EACH $75 $225 Telford - Aberdeen
Sta. 55+00 to Sta. 58+50 3 EACH $75 $225 Aberdeen - Forrer
Sta. 58+50 to Sta. 62+00 3 EACH $75 $225 Forrer - Lonsdale
Sta. 62+00 to Sta. 65+00 3 EACH $75 $225 Lonsdale - Greenmount
Sta. 65+00 to Sta. 68+50 3 EACH $75 $225 Greenmount - Dellwood
Sta. 68+50 to Sta. 71+50 3 EACH $75 $225 Dellwood - Gainsborough
TOTAL 49 EACH $75 $3,675
SHROYER ROAD - BIKE LANE SYMBOL
Sta. 13+00 to Sta. 71+50 55 EACH $49 $2,673 East Dorthy Lane - Gainsborough Rd
SHROYER ROAD - LTL ARROW
Sta. 13+00 to Sta. 71+50 26 EACH $65 $1,682 East Dorthy Lane - Gainsborough Rd
Concrete nose (island) 17 EACH $1,000 $17,000
Sign support, complete 1 EACH $12,000 $12,000 sign support and foundation
Construction Sub Total $306,000
Incidentals
Maintaining Traffic (1%) 1 LS $25,000 $25,000
Contract Perfromance Bond (1%) 1 LS $4,000 $4,000
Field Office MONTH $2,200 $0 Type B
Construction Layout Stakes (1%) 1 LS $4,000 $4,000
Mobilization LS $10,000 $0 Table 624.02-1
PDP Contingency Costs 1 LS $108,000 $108,000 35% Contingency
Sub Total + Incidentals $447,000
Inflation 1 LS $32,184 $33,000 7.2% Inflation for 2017 Construction
TOTAL $480,000